Measure K-14 Street Rehabilitation Program
YOUR TAX DOLLAR$ AT WORK

On November 4, 2014 Grover Beach voters approved Measure K-14, the Grover Beach Street Rehabilitation; Safety Improvement Bond Measure. In approving the measure, the City was authorized to issue up to $48 million in bond funds for the repair of local streets over the next 25 years. To date the City Council has approved the issuance of three bonds totaling $28 million in funds.

Completed Projects
The first $5 million bond issuance on February 17, 2015 funded three projects as outlined in the Completed K-14 Street Bond Project Map. These completed projects provided maintenance and repair of 84 city blocks or approximately 7 miles of roadway, representing 20% of all local streets. 

Current Measure K-14 Street Rehabilitation Project

At the City Council meeting on March 7, 2016, the Council approved the second bond sale of $8 million, which will provide maintenance and repair of 54 city blocks or approximately 4 miles of roadway as outlined below. Once completed, a total of 35% of local streets will have received maintenance and repair with Measure K-14 bond funds. 

  Project 2295-4 Street Rehabilitation Project

 Contractor: V. Lopez & Sons Engineering Contractors, Inc.
 Estimated Completion Date: July 2018
     CIP 2295-4 Street Rehabilitation Project - Project Map
     Weekly Construction Update05/14/2018
     South 13th Street - West Grand Avenue to Farroll Road
     Long Branch Avenue - Oak Park Boulevard to South 13th Street
     Newport Avenue - Front Street to North 4th Street
     North 16th Street - West Grand Avenue to Atlantic City Avenue
     3rd Street - Long Branch Avenue to northern city limit
     North 3rd Street – West Grand Avenue to Long Branch Avenue
     South 8th Street
     Mentone Avenue

 Project 2295-5 Street Rehabilitation Project  

 Contractor: JJ Fisher Construction, Inc.
 Estimated Completion Date: November 2018
     CIP 2295-5 Street Rehabilitation Project - Project Map
     Long Branch Avenue - South 3rd Street to South 10th Street

 Project 2295-6 Street Rehabilitation Project  

 Project Currently in Design Phase 
 Contractor: TBD
 Estimated Completion Date: TBD
     CIP 2295-6 Street Rehabilitation Project - Project Map
     Newport Avenue - North 4th Street to eastern city limit 

 Project 2295-7 Street Rehabilitation Project  

 Contractor: JJ Fisher Construction, Inc.
 Estimated Completion Date: October 2018
     CIP 2295-7 Street Rehabilitation Project - Project Map
     Front Street - North 1st Street to Carmelde Lane 
     Carmelde Lane
     North 1st Street - Front Street to Ocean View Avenue 
     North 2nd Street - Front Street to Ocean View Avenue 
     Ocean View Avenue - Front Street to North 4th Street

Future Measure K-14 Street Rehabilitation Projects
On November 6, 2017, the City Council authorized the third bond issuance of $15 million to fund the next round of street rehabilitation projects. At the City Council meetings of June 1, 2015, October 17, 2016, and February 20, 2018 meetings, the City Council prioritized streets for future projects as identified on the Proposed Future Project Map

Additional Information

  • For comments or concerns regarding street improvement projects, please contact the Grover Beach Public Works Department at (805) 473-4530 or send the department an email.
  • For construction updates and road closure information, see the Street Projects Facebook page at: Facebook.com/GroverBeachStreetProjects

Join us on TwitterJoin us on FacebookGrover Beach Government Access Local Channel 20
City Hall, 154 S. Eighth Street, Grover Beach, CA 93433 | City Hall Fax: (805) 489-9657
Calendar | Accessibility | Sitemap | Powered by CivicPlus | Copyright Notice