Measure K-14 Street Rehabilitation Program
YOUR TAX DOLLAR$ AT WORK

On November 4, 2014 Grover Beach voters approved Measure K-14, the Grover Beach Street Rehabilitation; Safety Improvement Bond Measure. In approving the measure, the City was authorized to issue up to $48 million in bond funds for the repair of local streets over the next 25 years. To date the City Council has approved the issuance of three bonds totaling $28 million in funds.

Completed Projects
As outlined in the Completed K-14 Street Bond Project Map, the City has expended a total of $13 million in bond funds for maintenance and repair of 154 blocks or approximately 12 miles of roadway, representing 40% of all local streets.

Current Measure K-14 Street Rehabilitation Projects
At the City Council meeting on November 6, 2017, the Council authorized the third bond sale of $15 million to fund the next round of street rehabilitation projects as outlined below:

 Project 2295-6 Street Rehabilitation Project  

 Contractor: TBD
 Construction Anticipated in Spring 2019
     CIP 2295-6 Street Rehabilitation Project - Project Map -  Project Design
     Weekly Construction Update: 5/20/2019
     Newport Avenue - North 4th Street to North Oak Park Boulevard

 Project 2295-7 Street Rehabilitation Project  

 Contractor: JJ Fisher Construction, Inc.
 Estimated Completion Date: February 2019
     CIP 2295-7 Street Rehabilitation Project - Project Map
     Front Street - Ocean View Avenue to N. 1st Street
     Carmelde Lane
     North 1st Street - Front Street to Ocean View Avenue 
     North 2nd Street - Ocean View Avenue, North
     Ocean View Avenue - Front Street to North 4th Street
     Newport Avenue - North Oak Park Boulevard to eastern city limit


 Project 2295-8 Street Rehabilitation Project


 Contractor: Souza Construction
 Estimated Completion Date: August 2019
     CIP 2295-8 Street Rehabilitation Project - Project Map
     Weekly Construction Update:  5/20/2019
     Park View Avenue, Front Street to North 4th Street
     Beckett Avenue, From Ramona Avenue to Brighton Avenue
     1st Street, Atlantic City Avenue to Ocean View Avenue
     North 2nd Street, Brighton Avenue to Newport Avenue
     Atlantic City Avenue, Front Street to North 8th Street

 Project 2295-9 Street Rehabilitation Project  

 Project Currently in Preplan Phase
 Contractor:
 TBD
Construction Anticipated in Fall 2019
     CIP 2295-9 Street Rehabilitation Project - Project Map
     South 16th Street, West Grand Avenue to The Pike

Future Measure K-14 Street Rehabilitation Projects
At the City Council meetings of April 6, 2015, June 1, 2015, October 17, 2016, February 20, 2018 and May 21, 2018, the City Council prioritized streets for future projects as identified on the Proposed Future Project Map. Please note, the map only shows those prioritized streets that are not currently identified as a project.  

Additional Information

  • For comments or concerns regarding street improvement projects, please contact the Grover Beach Public Works Department at (805) 473-4530 or send the department an email.
  • For construction updates and road closure information, see the Street Projects Facebook page at: Facebook.com/GroverBeachStreetProjects

Join us on TwitterJoin us on FacebookGrover Beach Government Access Local Channel 20
City Hall, 154 S. Eighth Street, Grover Beach, CA 93433 | City Hall Fax: (805) 489-9657
Calendar | Accessibility | Sitemap | Powered by CivicPlus | Copyright Notice